Privacy preferences
Inderes uses cookies to provide a better user experience and a personalised service. By consenting to the use of cookies, we can develop an even better service and will be able to provide content that is interesting to you.
  • Forum
  • Stock Markets
    • MarketsLive prices, indices, and market performance
    • Morning ReviewDaily market recap and key overnight highlights
    • Stock CalendarUpcoming earnings, listings, and corporate events
    • Dividends CalendarFuture and past dividends
  • Companies
    • CompaniesBrowse and filter the full list of listed companies
    • DiscoveryInspiration for your next investment
    • IPOsNew listings and upcoming public offerings
    • AGM InvitationsAnnual general meeting dates and shareholder info
  • Stock Research
    • ResearchExpert stock analysis and recommendations
    • ArticlesNews, insights, and market commentary
    • PortfolioInderes model portfolio
    • inderesTVVideo hub for stock research, analysis, and expert commentary
    • TranscriptsFull text records of earnings calls and investor meetings
    • Stock ComparisonCompare financials and performance across multiple stocks
    • Earnings SeasonCompare EPS estimates to reported results
    • Short SellingSee which listed companies have disclosed short interest
    • Compound Interest CalculatorSee how your savings grow with the power of compound interest.
Find us on social media
  • Inderes Forum
  • Youtube
  • Instagram
  • Facebook
  • X (Twitter)
Get in touch
  • info@inderes.se
  • +46 8 411 43 80
  • Vattugatan 17, 5tr
    111 52 Stockholm
Inderes
  • About us
  • Our team
  • Careers
  • Inderes as an investment
  • Services for listed companies
Our platform
  • FAQ
  • Q&A
  • Terms of service
  • Privacy policy
  • Disclaimer

Inderes’ Disclaimer can be found here. Detailed information about each share actively monitored by Inderes is available on the company-specific pages on Inderes’ website. © Inderes Oyj. All rights reserved.

Major data center contract in Forssa for Kreate

KREATEAnalyst Comment2026-10-22 08:02
Atte JortikkaAnalyst
Discuss

Summary

  • Kreate has signed an agreement with QTS for the earthworks contract of a data center campus in Forssa, enhancing its position in the growing data center construction market.
  • The contract involves moving nearly one million cubic meters of earth over seven months, starting in October, and will be recorded in Kreate's Q3 order book, which was already at a record-high of 886 MEUR at the end of Q2'26.
  • The Forssa project is QTS's first data center in Finland, with plans for up to ten buildings and a maximum IT capacity of ~630 MW, making it one of the largest in the country.
  • The scale of the campus infrastructure work is significant and likely to be spread over several years, with Kreate well-positioned for potential future phases due to its experience and early contract win.

This content is generated by AI. You can give feedback on it in the Inderes forum.

Translation: Original published in Finnish on 10/22/2026 at 8:05 am EEST.

Kreate announced on Wednesday that it has signed an agreement with QTS regarding the earthworks contract for the data center campus to be built in Forssa. The contract win strengthens Kreate's position in data center construction, which is an important and rapidly growing market for the company. The value of the contract was not disclosed. The company will report its Q3 results next Monday, at which point we will update our estimates and our view of the company.

According to the press release, the contract involves moving nearly one million cubic meters of earth in about seven months, with work set to begin in October. Kreate will record the contract in its Q3 order book, which was already at a record-high level of 886 MEUR at the end of Q2'26. According to the schedule, the contract will support volumes in late 2026 and early 2027, which is in line with our strong volume expectations. We expect Kreate's revenue to grow to 685 MEUR this year and to 737 MEUR next year.

Forssa is QTS's first data center project launched in Finland and one of the largest in the country. According to the project's EIA documentation, a maximum of ten data center buildings with a combined IT capacity of ~630 MW are planned for the ~150-hectare campus. In the more compact alternative, there would be six buildings and a capacity of ~440 MW. According to the statistics maintained by the Confederation of Finnish Industries, the capacity of the project is stated as 450 MW. It is our understanding that a building permit was granted for the first building in July. Based on the assumptions in our data center article and the capacity in the EIA (Environmental Impact Assessment), the scale of the campus infrastructure work could be quite significant, but overall it will likely be spread over several years. We aim to get more information from the company regarding the project size and potential in connection with the Q3 results (to be published on Monday, October 26). Data center campuses typically proceed in phases, and the implementation of later phases is not certain. However, we estimate that experience from around 70 data center projects and winning a contract with a new international customer already in the early stages of the project position Kreate well for any potential later phases of the project.

Kreate Group operates in the infrastructure sector. The company offers a wide range of services in the development of demanding industrial projects. Examples of services include bridge repair and construction, track construction for trains and rails, and mass excavation and crushing of rock for new motorway extensions. The largest operations are conducted around the Nordic market.

Read more on company page

Key Estimate Figures22/09

202526e27e
Revenue315.2685.3736.8
growth-%14.4 %117.4 %7.5 %
EBIT (adj.)10.034.037.8
EBIT-% (adj.)3.2 %5.0 %5.1 %
EPS (adj.)0.712.642.97
Dividend0.601.501.80
Dividend %4.8 %3.9 %4.6 %
P/E (adj.)17.614.713.1
EV/EBITDA8.38.57.4

Forum discussions

Here are the comments from Atte regarding that Kreate contract in Forssa Inderes – 22 Oct 26 Kreatelle merkittävä datakeskusurakka Forssaan ...
3 hours ago
by Sijoittaja-alokas
2
sttinfo.fi Kreate ja QTS yhteistyöhön Forssan datakeskushankkeessa | Kreate Group Oyj Vaativan infran rakentaja Kreate ja datakeskus- ja teko...
21 hours ago
by Cadel
6
Here is Atte’s preview ahead of Kreate reporting its Q3 results next Monday EDIT: I had broken the link in the previous message. It should work...
10/19/2026, 9:38 AM
by Sijoittaja-alokas
1
Did the management dare or manage to make good trades with the stock after all: Well, you can’t really say that they succeeded particularly ...
9/23/2026, 9:46 AM
by Karhu Hylje
10
I’ve also owned it a couple of times, but then always ended up selling with a small profit because something like this just couldn’t grow very...
9/23/2026, 7:48 AM
by Karhu Hylje
21
Since July, there have been three messages in the thread (and it wasn’t very active before this either); Timo Wikström’s presentation about ...
9/23/2026, 5:37 AM
by Sijoittaja-alokas
16
Today we were served some good and bad news. The bad news is that Timo Vikström is leaving the company. Inside information: Kreate has agreed...
9/22/2026, 2:04 PM
by Lohis
12