INSIDE INFORMATION: Linjemontage i Grästorp AB (publ) ("Linjemontage" or the "Company"), one of Sweden’s leading pure-play EPC providers within power infrastructure, has today received an award decision in a public procurement process from Svenska kraftnät relating to the construction of a new 400 kV power line between Oskarshamn municipality and Nybro municipality (the "Project"). The Project runs over three and a half years and has an estimated contract value of approximately SEK 1 billion. The award for the Project is subject to a statutory standstill period, which means that an agreement may be entered into no earlier than ten days from today.
The project involves approximately 98 kilometres of power line between Ekhyddan in Oskarshamn municipality and Nybro in Nybro municipality, and aims to strengthen the transmission grid, increase capacity and operational reliability, and reduce the risk of power cuts in the region. In recent years, Linjemontage has been awarded several major transmission projects by Svenska kraftnät. Among other things, the company is responsible for the construction of the new 400/220 kV substations in Plenninge and Jälla, outside Uppsala, which form part of Svenska kraftnät’s Uppsala package.
“The expansion and modernisation of the electricity grid is essential for industrial growth and Sweden’s continued electrification. The new transmission line between Ekhyddan and Nybro strengthens electricity transmission in southern Sweden and helps balance supply across the region. This is one of the largest transmission projects we have been awarded to date and, together with our ongoing substation projects in Jälla and Plenninge, demonstrates our ability to deliver large-scale and technically complex high-voltage projects. We thank Svenska kraftnät for the continued confidence in us and look forward to applying our expertise and experience to building a stronger electricity grid.” says Anders Åkerberg, CEO of Linjemontage.
The project is expected to commence at the end of 2026 and is scheduled for completion in June 2030. The works include, amongst other things, excavation and groundworks, foundation construction, the assembly and erection of steel pylons, cable laying, and the commissioning of the new facility.
The award decision regarding the Project is subject to a mandatory ten-day standstill period under the Act on Procurement in the Utilities Sectors (Sw. Lag (2016:1146) om upphandling inom försörjningssektorerna), which means that a contract may be entered into no earlier than after the standstill period has expired. During this period, the decision may be subject to review, and the outcome of the Project therefore cannot be guaranteed. The Company will inform the market of any changes in the Project process in accordance with the (EU) Market Abuse Regulation 596/2014 (MAR).
During the fourth quarter 2026, Linjemontage has also been awarded six new contracts with a total value of approximately SEK 314 million, in addition to those already announced in press releases. That total includes an award decision of approximately SEK 132 million that is currently under standstill period, and will be separately announced when the contract is signed.