Everyone, and thank you for taking the time to listen in today. My name is Marcus Tower. I'm the CEO of Hexicon, and I'll be now spending the next 20 or so minutes providing an update to our business at Hexicon, as well as providing an insight into the world of floating offshore wind and any related developments. Let me get to it. The agenda for the day is to start very briefly on floating offshore wind. Uh, give a bit of a view of where the market is today and where it's been very recently, and going into some key insights of Hexicon. And ending up with some highlights of our business during the last period. So let's get to it, and I'll start off with just a slide to summarize. Floating offshore wind. Many of you have listened to me before. Um, and for those repeating myself, Um, but it's worthwhile just to frame this in floating offshore wind, which has been dedicated to for about 15 years, is where you place turbines on floating foundations, which provides a lot of opportunities, not the least the fact that on a global scale, 80% of water's accessible for offshore wind or in deep water. So from a global perspective to really. Increase the part of the renewable energy mix that comes from offshore wind. It needs to be a significant part that is floating. What are the advantages then? Well, I've summarized them here in four words. One is environmentally friendly. It's less intrusion on the seabed and you're more flexible in where you site these projects. It means that you can avoid things like nature preserved areas, avoid conflicts with other marine life such as mammals, birds, and whatnot. Second is reliable. So, further off the coast, winds are stronger and winds are more stable. Additionally, the flexibility of not being constrained by water depth allows you to find the best wind locations. Third is scalable. So again, not constrained by patches of shallow water areas. Allows projects to be really big. It also allows projects to utilize one and the same foundation. So it's literally a blueprint copy across all the foundations in a really large wind farm, which is not the case if you consider bottom-fixed projects where every or every second foundation needs to be a specifically designed due to variations in water depth and seabed. And this is a true driver. To reach cost reductions is to make projects really big and industrialize across the complete supply chain. The last one is adaptable, so the ability to adapt to market conditions, the ability to place them where the demand is. And the fact of the matter is, as I said, there are 80% of waters across the globe are deep, and the vast majority of the power demand across the globe are in coastal areas. So with these four words summarizing floating offshore wind, which can be seen as the third generation of wind power, started onshore, then moved into waters, offshore in shallower waters, and then went deeper and deeper as the demand grew. And now we're at a transition, moving from fixed-bottom to also floating offshore wind. It hasn't been built on a commercial scale yet, but there are multiple projects across the globe, some that we are engaged in, that will start construction over the and next few years when it comes to floating technology. And looking at the market as such and where we are today. If we look back at last year, it was a challenging year for the industry. We did see a lot of projects being affected. We did see delays, and they were very much related to rising interest rates, inflation, and supply chain bottlenecks. So, many late-stage projects that were approaching the point of needing to make hardware decisions and investments were put on hold or even abandoned in some cases. With that said, we're noticing that many of our earlier or mid-stage projects, where a large portion of our portfolio lies, are not significantly affected from a cost perspective at this time. But certainly, the general market sentiments have been, I should say, weak across 2023. We're also seeing signals on the more positive fronts at the moment, with markets starting to stabilize. This clearly signals, related to the global economy, that inflation rates appear a little brighter. We are seeing some positive developments. Signals also exist in projects, but they haven’t really come back yet to where we were a few years ago. So for Hexicon, that means that we have seen somewhat longer lead times in any discussions that are related to transactions and investments into projects, etc. We are seeing a lot of consolidations across the market. Both various types of companies are merging, with bigger players coming in and taking over smaller players, so there's definitely some market consolidation being seen. Lastly, it's good to note that there are many political initiatives that have increased and continued to increase last year to support floating offshore wind. Boasting that across the EU, we're seeing it in the UK, and we're seeing it over in the US. It's related to things that are speeding up permitting processes. It's relating to increasing ceilings where there are subsidy schemes such as the UK and so on. So all in all, a challenging year behind us. Looking brighter ahead. How quickly markets will come back and stabilize. That is, of course, very hard to say, but certainly we're seeing it as a lot brighter looking forward than looking back at last year. A few key insights of Hexicon, just to summarize in four bullets. Number one, Hexicon has been working. Dedicated to floating offshore wind for 15 years. And that is a very unique experience to have. And that's taught us a lot across the years, both on technology and product development. Number two. Having our own fully owned IP for a competitive technology for TwinWind, which is a dual turbine floating foundation. I'll come back to that in a few slides, which is also very unique. And having that combined with product development expertise. Number three is a diversified portfolio. So we've purposely gone out for projects in markets that have certain prerequisites. That makes them very suitable for the specifics of floating offshore wind, rather than being in a certain region. So that means today, we are diversified across the globe, both geographically and in terms of maturity. And lastly, our whole fundamental business model and growth plan over the last six or seven years have been very closely linked to solid partnerships. So partnerships with both local and industrial players, and not the least, obtaining the local competence in various markets that we are active in, have been key ingredients in our growth. And we'll continue to play a significant part going forward. And just as a reminder, probably for some of you. But it is worthwhile mentioning that Hexicon operates with a dual business model in the sense that we're both a project developer and a technology provider. And these truly commercially reinforce one another. But they are also independent, and we run them independently at this stage. So until our technology, the floating foundation called TwinWind, is verified and demonstrated, we are treating and developing all projects on a technology-neutral basis. And the reasons for that are a few. But fundamentally, in any project development, you want to ensure that the project chooses whatever ingredients when it comes to technical components or any of the supply chain that are fit for purpose for this specific project. And that may vary widely because there are different parts of the world, different environments, different waves, water depths, etc. And also the fact that allowing projects to grow with maximum value increase and to allow investments to happen also during the development phase. You don't want to lock in projects to a specific technology too early. So that's how we operate these two parallel legs of the business model, if you will. But the learnings across the two and the opportunities they provide one another are substantial. So we are using the fact of having our own IP both to get into markets and to forge certain partnerships. And one slide on the technology. Um, we are focusing a lot on the technology. And I'll come back to it, in a few slides where we are revisiting and restructuring the TwinHub project, which is a demonstration project in the UK for our technology. But that doesn't mean that we're done prioritizing the technology as such. Um, so what we are doing is both. Generic technology developments, as well as specific engineering work with the key partners and suppliers for the TwinHub project. When it comes to the generic technical developments, we've carried out over the last eight to nine months, a significant technology assessment across a handful of different topics to ensure competitiveness. The market is growing very quickly, and there are probably over 70 different foundation technologies out there today. So we need to always assure ourselves that we're keeping this technology cutting-edge and competitive. And some of those areas for our technology are related to things like the control system, not only the control system of the individual turbines, but the control system of the overall system. So the two turbines on the same foundation, how they rotate, how they align with the wind, if they're misaligned with the winds, how long. What does that mean? It's related to the fabrication of it all, how to scale that, how to serially fabricate. It's related to the foundation weight, and it's related to the mooring system. So there are a few key and big aspects of this whole system that were carried out. Quite a significant assessment. And that makes us, you know, as confident as we've ever been that we're on the right track. And as a reminder, a key part of the driver for this technology has been to offer something that is truly long-term competitive. Placing two turbines on the same foundation is not going to be the first installation of a floating foundation, but we're out for the truly long-term play here. And why we're saying that is that with two turbines on the same foundation, you're able to install more turbines in a given area. That entails certain direct cost benefits. But it also allows a higher degree of. Coexistence with other stakeholders. So not occupying the same area allows it to be easier to avoid such conflicts. And also, if you look at it, waters are not endless, at least not the ones that are suitable for power production. So when you start layering different stakeholders and their interested areas on top of each other, you have an area over there and one area here and so on that are suitable. So to make most use of that area is key. That's going to be more and more important over time as more turbines are installed offshore. So that's where we're in for to really provide something that is meaningful over time, not just the ability to install the first floating wind turbine, but to install a competitive, long-term, scalable solution when it comes to the TwinHub works. Uh, all by reorganizing, uh, that developments. And there will be some schedule impacts for TwinHub that I'll come back to in a second. It's certainly so that some of the key areas, especially the engineering workstreams with suppliers, including the turbine supplier Ming Yang, are ongoing with the integrated work with the turbine supplier and the foundation supplier. That is key and that's ongoing right now, and it's truly exciting for our whole engineering team to ensure that the whole system works as one system confirmed by a turbine supplier. So that's a key step for any foundation supplier, and it's one that very few have crossed to date. It's picking up very quickly on the project developments as well. So this is just in this, you know, visualizing our three steps through the product development process and life cycle, if you will, to start by identifying and investing into projects. Uh, we very often originate so we start projects ourselves, grow them through project development. And then during the development phase, somewhere between the end of the early stage phase and up towards FID, when fabrication starts, is where we divest, sometimes through steps and sometimes in bigger chunks. And this is ongoing right now, across several projects and several discussions. Looking at that portfolio, it's spread between early stage, mid stage, and late stage. And currently, with our active projects, we've got nine that are in the early stage, none in the mid stage, and three in the late stage. And this is shown on this slide as well where we are spread out geographically. So, looking at the overall portfolio of projects where we have a participation interest. That's in total around 23 GW. And the net holding for Hexicon, that's Hexicon's ownership across these projects, is just shy of 13 GW today. So that's a substantial portfolio. And especially considering the force and the size of Hexicon and the main projects, I would say that are most advanced and in the largest scale, are in the three countries being Sweden, Italy, and South Korea. And if we talk about Korea specifically for a moment, we've announced previously the Sales and Purchase Agreement that was signed with Shell to take over their shares in the late stage project in South Korea called MunmuBaram. And there are many aspects to this. First and foremost, it's a project that is well positioned. A mature, healthy, sound project that is in one of the most promising floating offshore wind markets in the world. And why I say this, you know, Korea as a market, because there's a government-backed subsidy scheme for offshore wind that pays a premium that is higher the farther off the coast you are; it also pays an additional premium the deeper the water is. So this is, you know, really the sweet spot scheme for floating offshore wind. Why do the Korean authorities, you know, offer this? Well, it's their way to avoid conflicts. If you look at other uses of the sea, any of whatever that is, whether it's the fishing industry, shipping, leisure boating, and whatnot, those activities are higher in their activity, closer to shore. So to incentivize projects to be further off the coast, you minimize such conflicts. So that fits perfectly for floating offshore wind. Additionally, it's a market that has a really significant shipyard industry. So three out of the top 6 or 7 shipyards in the world are located in South Korea, and they are very suited to build floating structures as well as what they've typically done, of course, in shipping or oil and gas. But having the ability to have really high local content when it comes to jobs makes the political push to increase floating offshore wind more reliable long-term, and that it will be seen through regardless of political changes when it comes to the government. So the MunmuBaram project. Is not only the right way to go forward when it comes to the commercial aspects of the potential to actually gain revenue from it, but it's also a learning. So across some of these projects, South Korea and MunmuBaram is the most advanced large-scale projects that we have. And the ability to continue that and to control and run it, even though we won't be a 100% owner of it over time, of course. So we are in process to look at a new shareholding structure for it. We are really steering the developments right now and will continue regardless of the ownership structure, to have meaningful roles in the operations and developments of it, and that can be translated to a lot of the other projects that are of significant scale, but behind in terms of the development timeline, including Sweden, Italy, and South Africa. So this knowledge and learning experience through MunmuBaram that we've been active in for over six years now, how we're able to translate that to the rest of our portfolio is going to be a key ingredient in why we're making this move. And looking at the last quarter and some significant events. A key one was in the middle of the quarter, where we signed the Sales and Purchase Agreement to acquire 80% of the shares in the Brown project. As of that, we've also immediately initiated the process to establish a new ownership structure. So I want to make that clear that our ambition is not in any way to own a late stage, large project like this ourselves. About the opportunity, for various reasons, to acquire these shares. For a price that, in our view, is very favorable, creates an opportunity that is substantial. It is now ongoing, the regulatory approval process. And I'll come back to that in a bit as well, which is a key priority to close. But again, emphasizing that the regulatory approval process is ongoing, as well as setting a new ownership structure in parallel. Hopefully, we will be able to announce that in the near future, over the next few months with that agreement. And the choice we made to prioritize maneuvering. For all the right reasons. This is also partially a reason for us needing to reprioritize and slow down the development pace of the TwinWind projects in the UK. So, as I said before, some of the heavier engineering workstreams within that project are still running. We're still actively maturing the TwinWind technology as such, but the parts of that project related to the supply chain and the finalization of the construction are right now being reorganized. And we're revisiting all of that, not only in light of us putting a lot of effort towards Korea, but also reflecting on the markets and where that is. So we need to make sure that we're able to see through the construction of that project as well. And that's needed to force us, I should say, to reorganize and restructure parts of that project. So there will be some effects on the schedule of that project, and exactly what that means, We'll have to get back to you with. So, after the quarter, the one and a half months since. The end of Q1. I think it's fair to say that the main focus has been on the regulatory approval for the project. So there's a lot of documentation and material needed for us to get that over the line. And not only MunmuBaram, but we are also having discussions for partial divestments of additional projects. And it's on a similar theme. I want to just end by looking ahead as well. Where are our priorities? Priorities? Sorry. Well, in the short term, it's absolutely crystal clear that it's to get the regulatory approval, ensuring all shares are transferred. And then, as the second step, to establish that new ownership structure for the project, the long-term ownership structure. So again, these go in parallel. At the moment they're not closed. And we will be looking forward to coming back with new announcements over the general few months. In addition to that, we're of course not forcing anything else. So it is not everything we do, although it's near term and remains a very much priority. So we are having dialogues with additional projects, and for divestments, we will continue some key projects to mature, including looking at Sweden where we have three projects where we've applied for permits to the government. So we're waiting for decisions on all three of those large scale projects; one on the West Coast and two on the East of the coast. But also, of course, continue to grow. So this is not the utmost priority at the moment. But as divestments are also put in place and closed, we will look to secure additional projects and continue to develop, adding both new projects to the portfolio. But significant developments within some of these bigger projects that are already ongoing. So with that said, thank you very much for listening. And now I believe we've gotten some questions in for my colleague here. Pernilla will read them to me.